FORTY MOST ASKED QUESTIONS & ANSWERS

Time Required for the NEPA Process


35. How long should the NEPA process take to complete?

Answer:

When an EIS is required, the process obviously will take longer than when an EA is the only document prepared. But the Council's NEPA regulations encourage streamlined review, adoption of deadlines, elimination of duplicative work, eliciting suggested alternatives and other comments early through scoping, cooperation among agencies, and consultation with applicants during project planning. The Council has advised agencies that under the new NEPA regulations even large complex energy projects would require only about 12 months for the completion of the entire EIS process. For most major actions, this period is well within the planning time that is needed in any event, apart from NEPA.

The time required for the preparation of program EISs may be greater. The Council also recognizes that some projects will entail difficult long-term planning and/or the acquisition of certain data which of necessity will require more time for the preparation of the EIS. Indeed, some proposals should be given more time for the thoughtful preparation of an EIS and development of a decision which fulfills NEPA's substantive goals.

For cases in which only an environmental assessment will be prepared, the NEPA process should take no more than 3 months, and in many cases substantially less, as part of the normal analysis and approval process for the action.

--->


  • Home
  • Federal Register
  • Fed Land Management Laws
  • Fed Land Management Reports
  • Archives
  • Disclaimer
  • About us
  • Contact Us
  •   Copyright 2000-2020 NPLnews.com Contact Us / Disclaimer